Site: Morrisons Superstore - Verwood
Value: £3.2m
Date: 2014 - 2015
Contract
- Demolition of existing leisure centre & shopping precinct.
- Crushing for re-use on site
- Remediation of contaminated ground
- All groundworks associated with new superstore construction.
- Installation of Interceptors.
- Superstore floor slab
- Maintaining existing trading superstore throughout our works, demolishing upon completion to facilitate new carpark and petrol filling station.
What we did
- Assisted our client & Morrison’s throughout the duration of the project.
- Ensuring the existing store remained trading with no disruption.
Outstanding results
HWM Contracting Ltd delivered this challenging project on budget and on time.
Interim and final measurements were progressed during the contact with the final account agreement achieved at the end of the project.
HWM Contracting Ltd is a key Contractor for RG Group & we are currently partnering on several schemes at tender stage.